Construction Traffic Management Plans, Travel Plans, access details and other highways conditions, prepared and agreed so you can start on site.

How it works

Three steps, no wasted effort.

Check the wording

We read each condition and confirm exactly what the council needs to see.

Prepare the detail

Plans and drawings that answer the condition, nothing more and nothing less.

Agree it

We deal with the highways officer until the condition is discharged.

In detail

Conditions we regularly discharge.

Read: Five things highways officers look for at pre-app →

  • Construction Traffic Management Plans
  • Travel Plans and Travel Plan statements
  • Access and visibility details
  • Parking, cycle storage and EV charging details
  • Off-site highway works
  • Section 278 and Section 38 agreements (with your engineer)
FAQ

Questions we get asked

How long does the council have to decide?

Councils normally have eight weeks to decide an application to discharge conditions, unless you agree longer. Getting the detail right first time avoids a second round.

Do construction traffic effects matter under national policy?

Yes. The 2026 NPPF makes clear the highways tests apply during construction as well as once a scheme is built.

Can you help on a scheme where someone else did the planning work?

Yes. Send us the decision notice and the conditions.

In practice

What discharging a condition involves

Most planning permissions carry highways conditions. Some must be met before work starts, such as a Construction Traffic Management Plan. Others apply before anyone moves in, such as building the access and keeping visibility splays clear.

Each pre-commencement condition needs a formal application to the planning authority, with the details the condition asks for. The council consults the highway authority, so the information has to answer the officer’s questions first time.

  • We read each condition against its stated reason, so the submission answers what the council actually needs.
  • We prepare the plans, drawings and notes, and agree them informally with the highway officer where that saves a round of comments.
  • Where a condition is unclear or unreasonable, we say so early. Sometimes a variation is the faster route.

Last reviewed October 2026 by Ripple Development Planning. Policy and guidance change; for advice on a specific site, send us the details.